Open Letter to MassDOT Board Regarding I-90 Allston Multimodal Project

Share on Facebook
Share on Twitter
Share on
LinkedIn
+

June 22, 2020

Secretary Stephanie Pollack and Board of Directors

Massachusetts Department of Transportation

Re: I-90 Allston Multimodal Project, Boston, MA National Environmental Policy Act Review Scoping Report: All At-Grade Option and 8-lane Turnpike – Throat Area

Dear Secretary Pollack and Board,

Disruption is far too weak a word for what is coming to Metro-West commuters once the I-90 Allston multi-modal project gets underway in 2022. Long-term lane reductions along the turnpike stretching between Boston University and the Charles River will upend automobile travel to and from Boston.

Commuters, whose lives are going to be uprooted for at least a decade, should get the benefit of seeing cost differentials for both construction and long-term maintenance as well as project durations for alternative infrastructure design options. Therefore, it is in the public’s best interest to consider all at-grade option for the throat area of the I-90 Multimodal Project.

Pioneer Institute recommends that MassDOT revise its Scoping Report. Specifically, we recommend the addition of a modified at-grade option for I-90 and Soldiers Field Road in the throat area that includes the Paul Dudley White bicycle and pedestrian path (PDW) as a bridge over the river 30 to 40 feet from the riverbank.  Such an option would provide for parkland with neighborhood access or for the PDW to be positioned just north of Soldiers Field Road over the river’s edge (such positioning may require more narrow travel lanes and shoulders).

Additionally, the Institute

  1. Strongly advises against a reduction in the number of lanes on the turnpike. The toll-payers will likely be paying for the lion’s share of the project. Their forbearance with the disruptions of the construction period and their bearing the financial burden of paying for the project should not be rewarded with a design that reduces lane capacity below what it currently is.
  2. Urges MassDOT to maintain options to further improve the turnpike as technologies become available that will reduce congestion or enhance public safety.
  3. Urges that work on the turnpike structures over route 128 be undertaken before the start of the Allston project in order to avoid concurrent projects and thereby compound traffic woes. Those bridges are about eight years older than the BU viaduct, are also structurally deficient and in dire need of repair.
  4. Urges that Worcester Line service be ramped up to accommodate greater ridership during the construction period. Framingham and other points west have long endured snarled traffic due to at-grade crossings and increasing service will make traffic in downtown areas more severe. Pioneer recommends that at-grade crossings in the corridor be addressed concurrently with the planning of the I-90 Allston project.
  5. Supports a traffic study relative of measures and design changes to calm traffic on Soldiers Field Road so that policymakers have the information on the impact of eliminating lane capacity on routine commuters, affected towns, Memorial Drive, secondary roads and other side streets in the area.

Finally, Pioneer Institute recommends that the following additional actions be considered for mitigation:

  1. Maintain two-track Worcester Line service throughout the construction period
  2. Begin a pilot project to electrify key areas of the Worcester Line to improve commutes and increase ridership
  3. River restoration measures should consider co-location of other public benefits such as stormwater mitigation and public access. Due to the project’s close proximity and significant impact on the Charles River and surrounding parklands, river restoration should be a key element of the project.
  4. End plans for the West Station layover facility to avoid additional traffic on the Worcester Line
  5. Build platforms for completely level boarding at more commuter rail stations, beginning with Back Bay Station, to reduce dwell time
  6. Expedite certain proposed design upgrades for Newton’s commuter rail stops to improve access and facilitate faster peak-hour boarding
  7. Facilitate partnerships among the MBTA, communities, and private firms to increase parking capacity during project construction near the Green Line, Commuter Rail, and bus stations in the I-90 corridor
  8. Provide transparency on the plan to provide Kendall Square transit access from West Station to benefit commuters from the west
  9. Where practical, permanently expand station parking lots or consider higher-capacity garages
  10. Provide MBTA bus service for the I-90 corridor from Park and Ride lots to Boston during construction
  11. Conduct a feasibility study for improving the Newton Corner exit interchange, addressing design deficiencies of exit ramps and preventing traffic spillover onto I-90
  12. Encourage pedestrian and bicycle infrastructure improvements near existing Worcester Line and Green Line stations
  13. Increase MBTA coordination with the MetroWest Regional Transit Authority and the Worcester Regional Transit Authority, including expanded service during construction
  14. Install electronic speed limit signs that adjust to traffic conditions, maximizing road efficiency
  15. Create numerous opportunities for western commuters to provide feedback to MassDOT on these mitigation efforts, including public meetings, special web forums, and outreach efforts
  16. Ensure that residents from MetroWest and Central Massachusetts are represented on the MassDOT board throughout the construction period
  17. Establish the finance plan for the project in an open and transparent manner and form a finance plan task force with toll payer and other public representation
  18. Seek extensive federal funding for the project and continue to work with private organizations to help fund the project

Sincerely,

 

Mary Z. Connaughton, Director of Government Transparency

 

James Stergios, Executive Director

 

cc: Jeffrey McEwen, Regional Division Administrator, FHWA

cc: Steve Poftak, MBTA General Manager

 

Get Updates on Our Transportation Research

Study Documents The Design Challenges, Contracting Issues, And Delays Facing New MBTA Fare Collection System

This new study unearths previously unseen communications between the MBTA and its contractors, showing that the MBTA’s efforts to modernize its fare collection system, including allowing payments with credit cards and bringing “tap and go” technology to Commuter Rail and ferry lines, was riddled with technological challenges and difficulties overseeing contractors as early as 2019, culminating in a 3-year delay to the project’s full implementation.

Transit Innovation Explored: A Bus As Fast As A Train?

Hubwonk host Joe Selvaggi talks with transportation expert Ian Ollis about the findings of his new research paper, "Bus Rapid Transit: Costs and Benefits of a Transit Alternative," which examines the benefits of building Bus Rapid Transit to serve communities looking for faster transit alternatives to a car.

Study Finds Bus Rapid Transit Can Offer Cost-Effective Benefits

Bus rapid transit (BRT) incorporates unique features such as dedicated lanes to provide reliable and cost-effective service while reducing congestion and its detrimental environmental impacts, according to a new study published by Pioneer Institute.

Study Raises Concern That Annual T Fare Evasion Costs Could Rise By More Than $30 Million Under AFC 2.0

According to the Federal Transit Administration (FTA), the MBTA’s $935.4 million fare collection system (AFC 2.0) that is scheduled to be implemented in 2023 will reduce fare evasion by $35 million over a decade. But the T announced in 2021 that evasion could actually increase by up to $30 million under AFC 2.0, and now a Pioneer Institute study warns that insufficient fare enforcement could drive that figure even higher under the new system.

Pioneer Applauds MassDOT for Allston Project All At-Grade Plan

Pioneer Institute applauds the Massachusetts Department of Transportation (Mass DOT) for its decision to move forward with an all at-grade design for the “throat” area as part of the massive $1.7 billion Allston I-90 Interchange project announced yesterday by State Secretary of Transportation Jamey Tesler. Pioneer had proposed that MassDOT should revise its Scoping Report on the I-90 Allston Multimodal Project and recommend an additional option - a modified at-grade option for the throat area - to the Federal Highway Administration.

Enduring the Maelstrom: Lessons from MassPort Leadership During 9/11

Hubwonk host Joe Selvaggi talks with author and former MassPort CEO Virginia Buckingham about her recently released book, On My Watch: A Memoir, which chronicles her experience leading the organization through 9/11 and the life and leadership lessons learned from that tragic day.

MBTA Ridership Trends Compared to Public Transportation Agencies Nationwide

/
The COVID-19 pandemic had a devastating effect on our economy,…

The Effects of the COVID 19 Pandemic on MBTA Light Rail Ridership

/
In 2020, the COVID 19 pandemic had an unprecedented impact on…

Urban Cyclist Fatalities: Improving the Safety of Our Commuters

Pioneer set out to compare fatality data, miles of bike lanes, and cyclist commuter statistics in the five largest cities in the Northeast to develop recommendations for what urban areas can do to improve dangerous riding conditions. 

Open Letter: Extend the Term of the MBTA’s Fiscal and Management Control Board

Read Pioneer Institute's Open Letter urging policymakers to extend the term of the MBTA’s Fiscal and Management Control Board (FMCB), which is currently scheduled to sunset at the end of June.  The Letter also calls for the Control Board to continue to be made up of transit experts rather than political appointees, and recommends that an independent audit office be created that reports directly to the FMCB.

Traffic Strikes Back: New Transportation Strategies for Post-Pandemic Prosperity

Host Joe Selvaggi talks with Chris Dempsey, Director of Transportation for Massachusetts, about road and mass transit innovations that could address traffic challenges in a high-growth, post-pandemic economy.

Contracting with private providers could avert MBTA cuts

/
In response to a collapse in MBTA service in the winter of 2015, the newly formed Fiscal and Management Control Board (FMCB) set the authority on a course of bold reforms. The COVID-19 pandemic is once again presenting new and significant challenges to T leadership that require a rethinking of how service is delivered to stave off painful service cuts.