Open Letter to MassDOT Board Regarding I-90 Allston Multimodal Project

Share on Facebook
Share on Twitter
Share on
LinkedIn
+

June 22, 2020

Secretary Stephanie Pollack and Board of Directors

Massachusetts Department of Transportation

Re: I-90 Allston Multimodal Project, Boston, MA National Environmental Policy Act Review Scoping Report: All At-Grade Option and 8-lane Turnpike – Throat Area

Dear Secretary Pollack and Board,

Disruption is far too weak a word for what is coming to Metro-West commuters once the I-90 Allston multi-modal project gets underway in 2022. Long-term lane reductions along the turnpike stretching between Boston University and the Charles River will upend automobile travel to and from Boston.

Commuters, whose lives are going to be uprooted for at least a decade, should get the benefit of seeing cost differentials for both construction and long-term maintenance as well as project durations for alternative infrastructure design options. Therefore, it is in the public’s best interest to consider all at-grade option for the throat area of the I-90 Multimodal Project.

Pioneer Institute recommends that MassDOT revise its Scoping Report. Specifically, we recommend the addition of a modified at-grade option for I-90 and Soldiers Field Road in the throat area that includes the Paul Dudley White bicycle and pedestrian path (PDW) as a bridge over the river 30 to 40 feet from the riverbank.  Such an option would provide for parkland with neighborhood access or for the PDW to be positioned just north of Soldiers Field Road over the river’s edge (such positioning may require more narrow travel lanes and shoulders).

Additionally, the Institute

  1. Strongly advises against a reduction in the number of lanes on the turnpike. The toll-payers will likely be paying for the lion’s share of the project. Their forbearance with the disruptions of the construction period and their bearing the financial burden of paying for the project should not be rewarded with a design that reduces lane capacity below what it currently is.
  2. Urges MassDOT to maintain options to further improve the turnpike as technologies become available that will reduce congestion or enhance public safety.
  3. Urges that work on the turnpike structures over route 128 be undertaken before the start of the Allston project in order to avoid concurrent projects and thereby compound traffic woes. Those bridges are about eight years older than the BU viaduct, are also structurally deficient and in dire need of repair.
  4. Urges that Worcester Line service be ramped up to accommodate greater ridership during the construction period. Framingham and other points west have long endured snarled traffic due to at-grade crossings and increasing service will make traffic in downtown areas more severe. Pioneer recommends that at-grade crossings in the corridor be addressed concurrently with the planning of the I-90 Allston project.
  5. Supports a traffic study relative of measures and design changes to calm traffic on Soldiers Field Road so that policymakers have the information on the impact of eliminating lane capacity on routine commuters, affected towns, Memorial Drive, secondary roads and other side streets in the area.

Finally, Pioneer Institute recommends that the following additional actions be considered for mitigation:

  1. Maintain two-track Worcester Line service throughout the construction period
  2. Begin a pilot project to electrify key areas of the Worcester Line to improve commutes and increase ridership
  3. River restoration measures should consider co-location of other public benefits such as stormwater mitigation and public access. Due to the project’s close proximity and significant impact on the Charles River and surrounding parklands, river restoration should be a key element of the project.
  4. End plans for the West Station layover facility to avoid additional traffic on the Worcester Line
  5. Build platforms for completely level boarding at more commuter rail stations, beginning with Back Bay Station, to reduce dwell time
  6. Expedite certain proposed design upgrades for Newton’s commuter rail stops to improve access and facilitate faster peak-hour boarding
  7. Facilitate partnerships among the MBTA, communities, and private firms to increase parking capacity during project construction near the Green Line, Commuter Rail, and bus stations in the I-90 corridor
  8. Provide transparency on the plan to provide Kendall Square transit access from West Station to benefit commuters from the west
  9. Where practical, permanently expand station parking lots or consider higher-capacity garages
  10. Provide MBTA bus service for the I-90 corridor from Park and Ride lots to Boston during construction
  11. Conduct a feasibility study for improving the Newton Corner exit interchange, addressing design deficiencies of exit ramps and preventing traffic spillover onto I-90
  12. Encourage pedestrian and bicycle infrastructure improvements near existing Worcester Line and Green Line stations
  13. Increase MBTA coordination with the MetroWest Regional Transit Authority and the Worcester Regional Transit Authority, including expanded service during construction
  14. Install electronic speed limit signs that adjust to traffic conditions, maximizing road efficiency
  15. Create numerous opportunities for western commuters to provide feedback to MassDOT on these mitigation efforts, including public meetings, special web forums, and outreach efforts
  16. Ensure that residents from MetroWest and Central Massachusetts are represented on the MassDOT board throughout the construction period
  17. Establish the finance plan for the project in an open and transparent manner and form a finance plan task force with toll payer and other public representation
  18. Seek extensive federal funding for the project and continue to work with private organizations to help fund the project

Sincerely,

 

Mary Z. Connaughton, Director of Government Transparency

 

James Stergios, Executive Director

 

cc: Jeffrey McEwen, Regional Division Administrator, FHWA

cc: Steve Poftak, MBTA General Manager

 

Get Updates on Our Transportation Research

Clearing Boston’s Throat: What the I-90 Allston Project Portends for Metro West Commuters

/
Join hosts Joe Selvaggi and Pioneer Institute’s Mary Connaughton, and guest, former Mass. Secretary of Transportation Jim Aloisi, as they discuss the I90 Allston Multimodal Project, its long-term benefits, and their concerns for the metro west commuters and communities during the project’s decade-long construction.

During construction, the Allston Mass. Pike project must address commuters’ needs

/
As part of the state’s $1 billion reconfiguration of the Massachusetts Turnpike in Allston, Transportation Secretary Stephanie Pollack recently announced that a narrow strip of land known as “the throat,” will be considered for an at-grade option in addition to a proposal to rebuild the highway viaduct by Boston University.

COVID-19 Silver Lining: MBTA Takes Advantage of Ridership Lull to Accelerate $8.5 Billion Modernization Program

Pioneer Institute congratulates the Fiscal and Management Control Board (FMCB) and MBTA management for taking advantage of the precipitous ridership declines due to the COVID pandemic to dramatically accelerate ongoing construction projects.

A Time to Build

/
The MBTA is taking advantage of anemic low ridership from the…

Open Letter to MassDOT Board Regarding I-90 Allston Multimodal Project

/
Read Pioneer's Open Letter to MassDOT on the I-90 Allston Multimodal Project, Boston, MA National Environmental Policy Act Review Scoping Report: All At-Grade Option and 8-lane Turnpike – Throat Area

Survey Suggests Demand for Telecommuting After COVID-19 Crisis

Citing an avoidance of the commute and more flexible scheduling, nearly 63 percent of respondents to Pioneer Institute’s survey, “Will You Commute To Work When The COVID-19 Crisis Is Over?” expressed a preference to work from home one day a week, and a plurality preferred two to three days a week, even after a COVID-19 vaccine is available. Respondents cite social isolation as the biggest drawback of remote work. The survey was conducted from April 22nd to May 15th, and received responses from over 700 individuals.

It’s Time for the MBTA to Actively Engage Riders to Understand Their Commuting Plans

/
The MBTA should conduct a survey of mTicket app users regarding their future plans. Some may never work in offices again. Some will certainly do some workdays in the office and some at home. Others will be in offices and back to business as usual at some point. Using their responses, the T can calculate ridership and determine projected revenue.

Study Highlights Transit Agency Best Practices in Response to COVID-19

The MBTA is taking a number of important steps to mitigate risks associated with the coronavirus, but some transit agencies around the country - from Philadelphia to San Francisco - have done significantly more, according to a new study that highlights the best practices of U.S. transit systems in response to COVID-19.

WILL YOU COMMUTE TO WORK WHEN THE COVID-19 CRISIS IS OVER?

How will you look at commuting in the future? This survey will ask over 30,000 people how their attitudes and habits will change. Please be part of our work to understand the changing world around us.

MassDOT’s West Station design plans fall one track short

/
In 2014, MassDOT proposed the construction of West Station, a…

Open Letter to MA Governor Charlie Baker Regarding Boston Commuters from Points West

/
In an Open Letter to the Massachusetts Governor, Pioneer Institutes presents its concerns about the I-90 Allston Multimodal Project, and its impact on those who will be most affected during the project’s construction

A Control Board Equipped for the Next Phase of MBTA Reform

In a new policy brief out today, Pioneer Institute calls on the Massachusetts Legislature to extend the life of the MBTA’s Fiscal and Management Control Board beyond the current fiscal year ending on June 30, and adjust it to address the agency's new challenges.